Stoppages Results

Narrowboats cruising on the Peak Forest Canal in Disley

Works which make up part of the 2010-2011 winter stoppage programme have been highlighted in blue

Results 1-4 of 4

Peak Forest Canal »

  1. Restriction: MINIMUM NAVIGATIONAL HEADROOM OF 6'4

    28 Nov 2011 - 25 May 2012

    Associated Regional Office: Manchester & Pennine Waterways

    Restriction required to facilitate installation of temporary bridge for access to works site for United Utilities water quality improvement scheme.

    Please ensure your craft will fit under bridge of height of 6'4" prior to proceeding to navigate this section - THIS TEMPORARY BRIDGE WILL BE LOWER THAN SURROUNDING BRIDGES.

    THIS RESTRICTION WILL LAST FOR 25 WEEKS

    (Enquiries: 01782 785703)

  2. Towpath Closure only: PEAK FOREST CANAL BETWEEN BRIDGE A AND BRIDGE 1

    28 Nov 2011 - 06 Apr 2012

    Associated Regional Office: Manchester & Pennine Waterways

    The towpath will be closed for a duration of 18 weeks to facilitate United Utilities water quality improvement project.

    British Waterways apologise for any inconvenience this may cause.

    (Enquiries: 01782 785703)

  3. Stoppage: Strines Aqueduct

    01 Feb 2012 - 09 Mar 2012

    Associated Regional Office: Manchester & Pennine Waterways

    Canal de-watered and wash wall re-built to prevent leakage.

    (Enquiries: 01782 785703)

    The towpath is also closed

  4. Restriction: Marple aqueduct

    06 - 10 Feb 2012

    Associated Regional Office: Manchester & Pennine Waterways

    Vegetation clearance works at the aqueduct are required to be undertaken which are a first phase as part of the major works funded scheme to repair missing/ spalled sections of masonry on the scheduled ancient monument. The vegetation works will require roped access to remove all Ivy from the aqueduct walls and to remove all self set trees/saplings. The vegetation clearance works are expected to take one week.
    Access to both faces of the aqueduct via ropes will be required which will run across the navigation channel and towpath restricting un-impeded passage through the site.
    Navigation and towpath restriction between 8.00am and 4.30pm for up to 1hr.
    British Waterways apologise for any inconvenience

    (Enquiries: 01782 785703)