You are here:

Stoppage: Oakmeadowford Lock 16

Waterway: Caldon Canal »

From 09/01/2012 to 10/02/2012

Is Date Flexible?: This stoppage may be affected by the River Churnett going into flood affecting the dewatered lock and its works.

Assets affected:

  • lock

Reasons for work:

  • repair

De-watering of the lock chamber to undertake bottom end mitre gate replacement to reduce water loss. Inspection of paddles and fixtures to be repaired or replaced as required.

Nearest upstream winding: Flint Mill above Cheddleton Lock 13

Nearest downstream winding: Black Lion at Consall