Stoppage: Halls Lock 20W

Waterway: Huddersfield Narrow Canal »

From 09/03/2012 to 20/04/2012

UPDATE (20 April 2012): Navigation is now open

UPDATE (17 April 2012): British Waterways and its contractors are continuing to work in the lock and have experienced severe difficulty in removing the water from the lock floor.

This is due to the amount of leakage through the lock and the recent wet weather. Works to repair the floor cannot be commenced until this is done.

Whilst there is a possibility that the works could be complete in 14 days but there is a possibility it could take up to a month to repair the lock. We are sorry we cannot be more precise at this stage but will update the stoppage notice as soon as it possible to do so. These works are extra to the recent grouting works at the site following a failure during the commissioning stage, it is still unclear what has caused this failure.

British Waterways apologise for any inconvenience caused. ----------------------------------------------------

UPDATE (11 April 2012): Following the diver's investigations it is necessary to de-water the lock and carry out additional works to the lock floor.

A further update will be issued on Monday.

British Waterways apologise for any inconvenience caused. ----------------------------------------------------

UPDATE (05 April 2012): Divers are continuing to work in the lock to investigate the problem with the lock floor. This is a difficult operation due to the conditions on the lock floor and an accurate completion date cannot be given at this time.

The result of the investigations might require additional repairs to be carried out extending beyond Wednesday the 11th.

A further update will be published on Wednesday when more information will be available. ----------------------------------------------------

UPDATE (04 April 2012): Divers are being mobilised to site this afternoon to investigate the problem with the lock floor.

A further update will be given tomorrow morning.

British Waterways apologise for any inconvenience caused. ----------------------------------------------------

UPDATE (02 April 2012): Unfortunately a further problem was encountered with the lock while it was being recommissioned over the weekend. It is expected that this will take up to 48 hours to resolve, we anticipate that the lock will reopen on Wednesday morning 4th April.

British Waterways apologise for any inconvenience. ----------------------------------------------------

UPDATE (29 March 2012): Due to additional works we have had to extend this stoppage.

Passage is expected to be available on Monday, 2nd March around 8am. Assisted passages shall be in place for one week afterwards.

British Waterways apologise for any inconvenience caused. ----------------------------------------------------

To allow localised dewatering of lock chamber for major grouting works at Halls Lock 20w.

The navigation and towpath will be closed between Locks 21 and 20 West to allow installation of grout into lock chamber and towpath approach to seal extensive leakage.

British Waterways apologise for any inconvenience.